Description Final installation and commissioning of 6 steam turbines/ compressor units (single shaft)
Personnel 2 Commissioning Engineer – 2 Field Service Supervisor – 1 Software Engineer
Project Name KAVIAN
Site Location
Assalouyeh, Kavian
Period August 2011 – October 2012

 

27. August 2011

Iran, AssalouyehKAVIANFinal Installation a. COM.

[…]
29. July 2011

Taiwan, TaipehFCFC 8779 & 8868Maintenance

[…]
30. June 2011

Taiwan, TaoyuanFCFC 8969 & 8970Troubleshooting

[…]
30. June 2011

Taiwan, TaipehFCFC 12124Troubleshooting

[…]
30. March 2011

Taiwan, TaoyuanOPTC 8555/ 8556Maintenance

[…]
30. January 2011

Taiwan, TaipehFCFC 8867 & 8868Maintenance

[…]
30. January 2011

Oman, SalalahSALALAHTroubleshooting a. COM.

[…]
10. November 2010

Taiwan, TaipehNAN YA 8663Maintenance

[…]
10. November 2010

China, YulinYULINTroubleshooting a. COM.

[…]
11. October 2010

China, YinchuanYINCHUANLoop Checks

[…]